| Under Construction
Loan Requirements
Information is provided here in the following sections:
- the most important requirement is compliance with all SIMBIOS
terms and conditions
- in addition, there are some further items that should be taken
into consideration: general
logistics such as deployment methods, ship needs, lab space etc. and
then there's the
- post cruise responsibilities.
SIMBIOS Terms and Conditions
The loan request MUST be made through the SIMBIOS project office.
The instrument pool section of the SIMBIOS website contains
instructions, guidelines and everything you will need to know:
Purpose, Deployment Policy, Loan Procedures, Loan Agreement,
Instrument Loan Form, Instrument Descriptions and Instrument
Schedules.
LOGISTICS
If you fulfill all SIMBIOS terms and conditions, and the item is
available loan (SIMBIOS keeps a cruise schedule for all their pool
instruments, there is also a cruise schedule here for our group)
there are some further logistical considerations.
BARNSTEAD SPECIFICATIONS
The Barnstead shipping case is 28" x 28" x 22" and
weighs approx. 70lbs, there is also a box of ancillary equipment
2'8" x 1' x 1'6" weighing about 50lbs.
The ancillary equipment consists of: the pre-filter canisters and
sections of garden hose to connect them, the pre-filters, the 4 main
filters, dispenser nozzle and tubing, cowling for the dispenser, and
another length of tubing to go from the unit to pre-filters.
The size of the actual Barnstead water maker requires the
following dimensions of bench space:
32" width
26" tall.
18" depth (with a further
20" to allow opening the front access door - this is not
usually a problem for a unit facing front on a bench and is not a
common action)
Preferably it should be sited next to a sink, where the
pre-filters can sit. If this is not possible, the pre filters will
add an additional 10" to the width dimension of bench space,
and a length of garden hose long enough to extend from wherever the
lab water supply is to the Barnstead unit. The dispenser nozzle is
on the end of 6' of tubing. The power requirement for the Barnstead
is 120V AC, 50-60 Hz.
Time:
Approx. 2 hours set up.
Approx. 2 hours break down and pack up.
HISTAR PACKAGE SPECIFICATIONS
Packing List:
The packing list will vary from cruise to cruise depending on many
factors. However as a guideline the absolute minimum is as follows:
| SMODAPS deck unit |
Instrument Case |
2'4" x 3' x 2' |
140lbs |
| Sea cable |
Wooden Crate |
4'4" x 1'6" x 2'2" |
160lbs |
| Instruments + cage |
Wooden Crate |
3'4" x 4'8" x 3' |
200lbs |
| Floats and line |
Trash Can |
2'2" x 2' diameter |
60lbs |
| Water calibration box |
Wooden Crate |
2' x 1'4" x 2'3" |
70lbs |
| Miscellaneous supplies |
Instrument Case |
2'3" x 2'3" x 2' |
90lbs |
| Laptop |
|
|
|
For the calibrations a high purity water source will be required.
This is usually going to be one of the Barnstead
units.
People
Although this package comes with a technician, at least 2 more
people are needed to help profile. Deployment and recovery
operations may take several more depending on the set up. Other than
explaining normal on-the-deck safety guidelines to get the package
into and out of the water (and whatever ship procedures exist),
there is a minimal amount of training required for any operators.
The HiStar package is designed to free fall, hence there are very
real dangers of the package drifting underneath the ship if care is
not taken by the operator on deck or the bridge officer on watch.
For this reason the ship's officers will also be given a run down of
the operation and what is required of the ship.
Ship Needs
- Lab Space: The MODAPS deck unit is usually best secured on the
floor of the lab (2'4" x 3' x 2'). In addition there should be
about 4ft of bench space adjacent to the Deck Unit for its monitor
and keyboard, and a laptop and printer.
- Deck Space: The cage and sea cable box need to be stored
securely close to the point of deployment.
- Winches/Deployment etc: In order to get the HiStar package into
and out of the water, there are a couple of options depending on
what is available and the ships' own set up.
The sea cable is not really designed to take the weight of the
package in air. However it is fine to take the weight in
water, when pulling the package up to the surface after a profile.
Hence an alternative line or cable should be set up to take the
weight to get the package in and out of the water. Generally the
packages' block will require space on an A frame type rig this will
run the sea cable during the profiles. If the ship has a winch wire
or air tugger available over a second block, we have a Sea Catch
quick release that can be utilised for deployments, and a mooring
hook on a boat hook for recoveries. If no wire is available, but a
capstan is, it is possible to attach a length of Dacron to the
package to be used as the lifting means. With this, a second block
is optional as the package block can be shared. A ship's crane if it
exists is another possibility if an A frame is not available to take
the block(s).
Time:
Set up:
approx. 5 hours
Pack up:
approx. 5 hours
Per 200m Profile: approx. 45 mins
1-2 hours per day for calibrations
POST CRUISE RESPONSIBILITIES
These are part (and only part) of the SIMBIOS agreement and are
merely re-stated here.
Data submission is the responsibility of the PI.
"The instruments will only be deployed on cruises that agree
to provide to SeaBASS at least minimally complete validation data
sets. Data submitted should conform to the SeaBASS format."
"The instruments will be deployed only by NASA-sponsored
PI's on cruises providing data to SeaBASS, on a timely schedule (ca.
3-months following completion of the cruise), for SIMBIOS ocean
color validation research"
Cost
"All shipping and other expenses associated with the use and
deployment of the loaned instrument are the sole responsibility of
the investigator. "
"The investigator shall be responsible for any damages to
the instrument incurred during the loan period" |